Name of client : Agency for Development (AFD) & Egyptian New and Renewable Energy Authority (NREA)
Location : Egypt
Key services : Technical Assistance
Year : 2013-2018
The objective of the project : Technical assistance for the tendering and project completion follow up for a 200MW Wind farm feasibility study in the Gulf of Suez.
.
Services provided :
- Technical preliminary study and assistance to the NREA in the field of the preparation of the feasibility study for wind power plants
- Tender writing, evaluation, and implementation as well as supervision of ongoing work until completion